RESOURCE-WEIGHTED PROJECT CONTROLS

Progress Measurement Sheet (PMS)

Turn Primavera P6 resource assignments into activity weights and resource-unit progress. Resource consumption is not proof of physical completion.

SEE THE METHOD BEFORE YOU UPLOAD

One resource-loaded XER becomes an auditable progress register.

PlanProof uses the resource units already assigned in Primavera P6. It does not invent activity weights or replace the project's approved measurement rules.

01

Load the XER

Read activities, WBS structure and resource assignments directly from the exported schedule.

02

Calculate weight and progress

Activity weight = activity budgeted resource units ÷ total project budgeted resource units.

03

Roll up and export

Review activity and WBS results, then export the evidence as professional PDF or Excel output.

Illustrative calculation2,500 activity units ÷ 100,000 project units = 2.50% activity weight40% activity progress × 2.50% weight = 1.00% earned project progress
  • Budget, actual and remaining units remain visible.
  • Activity resource progress is capped at 100%; WBS raw-unit rollups can exceed 100%.
  • Mixed unit types must be reviewed before contractual use.
  • Local processing and exports are free, without sign-in.

Analytics preferences

Optional first-party analytics use a random browser identifier to record pages viewed, selected product events, referring domain and country-level location. Raw schedule content and IP addresses are not stored in these analytics. You can reject analytics and keep using PlanProof.

Current choice: No choice saved

Necessary sign-in and service storage are separate from optional analytics. Your choice is saved in this browser when local storage is available.

Privacy information