Resource-weighted progress: state the denominator

Calculate transparent activity weights and distinguish consumed units from completed work.

“Progress” is not a single number. Agree the measurement basis before adding activities together. PlanProof’s Progress Measurement Sheet (PMS) resource indicator uses actual units divided by budgeted units; it does not independently measure installed quantities or earned value.

STEP 1

Use a coherent budget basis

Check TASKRSRC assignments, budget quantities and resource units. Labour hours, equipment hours and material quantities are not interchangeable. Prepare an export on a consistent, approved basis; the current tool does not normalise mixed resource units for you.

STEP 2

Calculate the activity weight

Divide each activity’s budgeted resource units by the total budgeted units in the included project. A 100-hour activity in a 400-hour scope has a 25% weight. Check unbudgeted activities and missing assignments; excluded scope will change the denominator and the apparent progress.

STEP 3

Name the progress formula

PlanProof calculates activity resource progress as actual/budget, capped between 0% and 100%, and multiplies it by the activity weight. Oracle P6’s Units % Complete uses actual divided by actual-plus-remaining. These can differ when the forecast changes. Neither quantity automatically verifies physical completion.

STEP 4

Reconcile consumption and output

Compare the resource result with accepted physical quantities, remaining-unit forecasts and the approved measurement method. Investigate high consumed hours with low physical output. Keep raw actual and remaining units visible even when an activity percentage is capped, so overruns are not hidden.

WORKED EXAMPLE

Hand calculation: 400 labour-hour budget

ActivityBudget / actualWeightResource progressProject contribution
A110100 h / 50 h25%50%12.5 percentage points
A120300 h / 0 h75%0%0 percentage points
Total400 h / 50 h100%—12.5% resource indicator

If 50 hours have been consumed but only 20% of A110’s physical work is accepted, its physical contribution on the same weight would be 5 percentage points. Label both measures; do not call 12.5% verified physical progress.

Take this checklist into the review

  • Resource units share a justified aggregation basis
  • Positive budgets and missing assignments checked
  • The denominator and included scope are recorded
  • Actual/budget distinguished from P6 actual/(actual+remaining)
  • Physical output and forecast overruns reviewed separately
PUT IT INTO PRACTICE

Run the 400-hour Progress Measurement Sheet (PMS) demonstration

Inspect the weights, reproduce the 12.5% result and download the same resource fixture and outputs.

Open the free demonstration →

Further reading

These guides describe PlanProof’s current implementation and a suggested review workflow. External references provide broader scheduling context; they do not endorse or certify this tool.

References checked 6 October 2026. PlanProof methodology · Scoring model

Analytics preferences

Optional first-party analytics use a random browser identifier to record pages viewed, selected product events, referring domain and country-level location. Raw schedule content and IP addresses are not stored in these analytics. You can reject analytics and keep using PlanProof.

Current choice: No choice saved

Necessary sign-in and service storage are separate from optional analytics. Your choice is saved in this browser when local storage is available.

Privacy information