← All practical guidesGUIDE 05 · 6 min READ · UPDATED 6 OCTOBER 2026

Recovery reviews: demand a credible route to completion

Test the assumptions behind a recovery proposal before accepting a cleaner score or earlier date.

A recovery review asks whether a proposed execution plan can be delivered. A quality score helps identify questions, but cannot prove crew availability, access, productivity, approval or achieved time recovery.

STEP 1

Fix the reference and status

Keep the accepted update, reporting date, contractual completion milestone and any approved extensions identifiable. Resolve material status contradictions first. A recovery proposal built on future actuals or unreported remaining scope does not give a dependable starting position.

STEP 2

Challenge every time-saving edit

Compare remaining durations, relationships, calendars, constraints and additions or deletions. For each proposed reduction, request the execution reason: added resources, changed method, released access or an approved scope decision. Record who controls the assumption and when it must be confirmed.

STEP 3

Review resources and interfaces together

Check whether parallel activities compete for the same crew, equipment, permits or workface. Review procurement and acceptance interfaces as well as construction work. Identify the trigger dates and contingency actions if the planned release or productivity does not materialize.

STEP 4

Recalculate, review and monitor

Run the proposed programme in P6 with documented scheduling settings. Review the driving path, near-critical paths and milestone movement. Agree leading indicators and a short reporting cycle. Keep the proposed recovery, approved revision and achieved progress separate in the narrative.

WORKED EXAMPLE

The sample clears flags; the reviewer still has decisions

Sample evidenceWhat it provesWhat remains to verify
A130 duration shortenedThe supplied duration changedFeasible method, crew, productivity and retained scope
Negative-float findings removedExported float values no longer trigger PP-201Controlled CPM result and accepted completion obligation
Score improves to 100No configured rule exceptions in that fixtureAchievability, approvals and actual recovery

The demonstration deliberately does not claim recovered days. Its float values were edited for teaching; it is not a P6-recalculated recovery case study.

Take this checklist into the review

  • Reference update and completion obligation identified
  • Every duration and logic change has supporting evidence
  • Resources, access and interfaces checked
  • Controlled P6 recalculation reviewed
  • Owners, trigger dates and fallback actions agreed
PUT IT INTO PRACTICE

Work through the recovery-review demonstration

Inspect the known edits, their score effect and the decisions the software cannot make.

Open the free demonstration →

Further reading

These guides describe PlanProof’s current implementation and a suggested review workflow. External references provide broader scheduling context; they do not endorse or certify this tool.

References checked 6 October 2026. PlanProof methodology · Scoring model

Analytics preferences

Optional first-party analytics use a random browser identifier to record pages viewed, selected product events, referring domain and country-level location. Raw schedule content and IP addresses are not stored in these analytics. You can reject analytics and keep using PlanProof.

Current choice: No choice saved

Necessary sign-in and service storage are separate from optional analytics. Your choice is saved in this browser when local storage is available.

Privacy information