Progress integrity: trust the update before the forecast

Check status, actual dates and sequence before interpreting a completion date.

A polished forecast is only as useful as the status behind it. Use the reporting cut-off as the reference, then reconcile activity status and actual dates with the records accepted for that period.

STEP 1

Confirm the cut-off

Record the XER data date and the reporting period. Verify that the latest recalculation date represents the intended cut-off. Identify missing dates and ambiguous date formats before treating a clean validation score as evidence of a reliable update.

STEP 2

Reconcile status with records

Inspect completed activities without an actual finish, not-started activities with an actual start, and any finish entered without a start. Compare each entry with agreed site records, inspection releases or handover evidence. Correct the source record rather than concealing the discrepancy with a constraint.

STEP 3

Investigate sequence in context

A started successor with an incomplete predecessor needs explanation. Review whether the relationship is FS, SS, FF or SF, whether a lag applies and whether the status is complete. Discuss the chosen scheduling options in P6. An intentional SS overlap must not be treated as an automatic error.

STEP 4

Separate the kinds of progress

Check what each percentage represents. Oracle distinguishes duration, units and physical percent complete; a physical percentage can be manually entered or based on activity steps. Keep quantity acceptance and consumed hours visible instead of replacing one with the other.

WORKED EXAMPLE

A140 starts after the data date

FieldSample valueInterpretation
Data date1 September 2026Reporting reference
A140 actual start12 September 2026PP-703: actual is later than the cut-off
Predecessor A130IncompletePP-502: review the sequence and source status

Do not just move the data date to clear the warning. First establish which date and status are supported by the reporting records.

Take this checklist into the review

  • Data date agrees with the reporting cut-off
  • Actual starts and finishes are supported by records
  • Future actuals resolved or the reporting date corrected with approval
  • Sequence warnings reviewed by relationship type
  • Resource consumption kept separate from physical completion
PUT IT INTO PRACTICE

Inspect the progress-integrity demonstration

Follow A140 from its future actual to the specific PP-502 and PP-703 evidence.

Open the free demonstration →

Further reading

These guides describe PlanProof’s current implementation and a suggested review workflow. External references provide broader scheduling context; they do not endorse or certify this tool.

References checked 6 October 2026. PlanProof methodology · Scoring model

Analytics preferences

Optional first-party analytics use a random browser identifier to record pages viewed, selected product events, referring domain and country-level location. Raw schedule content and IP addresses are not stored in these analytics. You can reject analytics and keep using PlanProof.

Current choice: No choice saved

Necessary sign-in and service storage are separate from optional analytics. Your choice is saved in this browser when local storage is available.

Privacy information